| Description of Current status as on 16/08/2020 |
- Piling works of Skew bridge completed.
- Anchor block casting in progress at Champakkara canal side.(anchoring 70% completed at Champakkara canal side)
- Canal side cleaning in progress
- Precast pile shifting from Pandapilly casting yard to site completed
- Desilting 80% completed
- Desilting 1810m completed out of 2170m
- Pile and slab 660m (running length) completed
- Piling for foot bridge completed
- Boat Jetty construction completed
- Pile load test for skew bridge completed
|