test

PROJECT STATUS OF WRD-KIIFB PROJECTS Last updated on 18/05/2021 Sl no Project Name District Amount Work Status Physical Progress Financial Progress 1 Modernisation of Water Transport in Alappuzha Canals – Phase 1 ALP AS: 88.93TS: 44.36 MAIN CANALS Cleaning and desilting completed in Town Canals Pile and slab work completed Stone masonry completed CULVERTS WORK…

Completed Projects

Punnamada Renovation of Tourism Office and Surroundings after flood-2018-details Completed Projects, ProjectsJune 28, 2020 Read more Development of Backwater Circuits in Alappuzha Backwater region as a mega circuit in Kerala Completed Projects, ProjectsJanuary 12, 2020 Read more The Karapuzha Tourism Project. 1st & 2nd Phase Completed Projects, ProjectsJanuary 12, 2020 Read more Development of Pandanadu…