Construction of groynes along the selected reaches of the Alappuzha District in Kerala State-KIIFB
1.CONSTRUCTION OF GROYNE BETWEEN CESCP 645 and 672 (Ch 77.34 km to Ch. 82.74 km) AT AMBALAPUZHA SOUTH, NORTH PANCHAYATH AND PUNNAPRA SOUTH PANCHAYATH
Name of the Project Engineer | M A Faseela Nasar | |
Physical Progress (%): | 10 | |
Date | Detailed Daily Report | Activites Planned for the Next Day |
11.06.2021 | 1. Tetrapod casted: 2T(28 nos.) and 5T(zero) 2. 2T and 5T Tetrapod laying for the Groyne(G1 and G3) in progress |
1. 2T and 5T Tetrapod casting 2. Laying of boulders, 2T and 5T tetrapods at G1, G3, G4 and G6 |
2.CONSTRUCTION OF GROYNE AT KATTOOR FROM CH.168.465 KM TO CH.171.627 KM (Old CH 96.643KM TO CH 99.535 KM).
Name of the Project Engineer | M A Faseela Nasar | |
Physical Progress (%): | 4 | |
Date | Detailed Daily Report | Activites Planned for the Next Day |
11.06.2021 | 1. Tetrapod casted: 2T(39 nos.) and 5T (4 nos.) | 1. 2T and 5T Tetrapod casting |
3.KIIFB PROJECT-CONSTRUCTION OF 21NOS GROYNES AT ARATTUPUZHA IN BET.CH.56.6 TO 57.8 KM AT ARATTUPUZHA
Name of the Project Engineer | SILPA R | |
Physical Progress (%): | 0 | |
Date | Detailed Daily Report | Activites Planned for the Next Day |
12.06.2021 | - | - |
4.KIIFB PROJECT-CONSTRUCTION OF 13NOS GROYNE AT PATHIYANKARA IN BET.CH.60.1 TO 61.6KM AT THRIKKUNNAPUZHA
Name of the Project Engineer | SILPA R | |
Physical Progress (%): | 2 | |
Date | Detailed Daily Report | Activites Planned for the Next Day |
12.06.2021 | The total no of tetrapods casted : 2T: 19 nos.(cumulative 2281) 5T: 0(cumulative: 93 nos.) |
1. 2T and 5T Tetrapod casting |
5.KIIFB PROJECT - CONSTRUCTION OF16 NOS GROYNE AT VATTACHAL IN BET. CH.53.4 TO CH.55.2 KM(1.8KM) AT ARATTUPUZHA GP
Name of the Project Engineer | SILPA R | |
Physical Progress (%): | 2 | |
Date | Detailed Daily Report | Activites Planned for the Next Day |
12.06.2021 | 1. 2T Tetrapod casted on date: 28 (cumulative 2097) 2. 5T tetrapod casted-0 |
1. 2T Tetrapod casting |