Name of the Project: Construction Of 13 nos Groyne at Pathiyankaral in Thrikkunnapuzha Gp
Name of the Project Engineer: Silpa R
Physical Progress (%) :2
Date | Detailed Daily Report | Activities Planned for the Next Day |
---|---|---|
11.06.2021 | The total no of tetrapods casted on date: 2T: 38 nos.(cumulative 2355) 5T: 0(cumulative: 93 nos.) | 1. 2T and 5T Tetrapod casting |