Last update on 24-10-2024 12.49 PM
Name of the Project: Construction of groyne field at Kattoor from chainage 168.465 to 171.627 KM (Old C99.535 KM ) at Alappuzha district
Name of the Project Engineer: M A Faseela Nasar
Physical Progress (%) :10
Date | Detailed Daily Report | Activities Planned for the Next Day |
---|---|---|
11.06.2021 | 1. Tetrapod casted: 2T(28 nos.) and 5T(zero) 2. 2T and 5T Tetrapod laying for the Groyne(G1 and G3) in progress | 1. 2T and 5T Tetrapod casting 2. Laying of boulders, 2T and 5T tetrapods at G1, G3, G4 and G6 |